Use this MOT Type 1 calculator to estimate how much Type 1 sub-base you need for a driveway, patio, path or foundation. Enter the area length and width, your required compacted depth and a wastage allowance, and the tool returns the compacted volume in cubic metres, the estimated tonnes of MOT Type 1, and the number of bulk bags and 25 kg bags to order — in metric or imperial.
Enter your sub-base details
Driveway: 100–150 mm
Recommended: 10–20%
MOT Type 1 required
Based on a typical compacted bulk density of 2 tonnes per m³. Actual density and bag weights vary by supplier — confirm before ordering.
Results are estimates only. Confirm quantities, material densities, pack sizes, product yields and specifications with your supplier or tradesperson before ordering. See our disclaimer for details.
How the calculation works
The calculator multiplies your area (length × width) by the required compacted depth to find the compacted volume of MOT Type 1 in cubic metres. Lengths entered in feet and depths in inches are converted to metric automatically.
Volume is then converted to tonnage using a typical compacted bulk density of 2.0 tonnes per cubic metre for MOT Type 1. Actual density varies with grading, moisture content and how well the material is compacted, so this is a planning figure only.
A wastage allowance is added on top for compaction, settlement, uneven ground and spillage. MOT Type 1 compacts significantly when whacked down, so a 10–20% allowance is typical when ordering by compacted volume.
The tonnage is converted into an approximate number of 850 kg bulk bags and 25 kg bags so you can order in whichever format your supplier sells.
Worked example
A driveway sub-base 5 m long by 4 m wide, compacted to 100 mm deep, with a 10% wastage allowance:
- Convert depth: 100 mm = 0.1 m
- Compacted volume = 5 m × 4 m × 0.1 m = 2.0 m³
- Add 10% wastage: 2.0 × 1.10 = 2.2 m³
- Weight = 2.2 m³ × 2.0 t/m³ = 4.4 tonnes
- Bulk bags = 4,400 kg ÷ 850 kg ≈ 6 bags
You would need roughly 2.2 m³ of MOT Type 1 — about 4.4 tonnes, or 6 bulk bags (around 176 × 25 kg bags).
Practical guidance on wastage
MOT Type 1 is sold loose but laid compacted, so it loses a meaningful amount of its loose volume when whacked down. If you enter the compacted depth (the finished depth you need after compaction), a 10–20% wastage allowance covers compaction losses, uneven ground and spillage. If you enter the loose depth instead, do not add a wastage allowance — the compaction factor is already built in. Wet Type 1 weighs more and compacts differently, so confirm the density and bag weights with your supplier before ordering.
Common unit conversions
- 1 m² at 50 mm compacted depth0.05 m³ of MOT Type 1
- 1 m² at 100 mm compacted depth0.1 m³ of MOT Type 1
- 1 m² at 150 mm compacted depth0.15 m³ of MOT Type 1
- 1 cubic metre of MOT Type 1≈ 2.0 tonnes (compacted)
- 1 bulk bag (850 kg)≈ 0.4–0.45 m³ compacted
- 1 cubic metre35.31 ft³ / 1.31 yd³