How Much Type 1 for a Patio
For a patio, work out the MOT Type 1 quantity by multiplying the patio area in m² by the compacted depth (typically 100–150 mm) and a density of about 2.0 t/m³. A 20 m² patio at 100 mm needs about 4 tonnes before wastage.
Patios carry only foot traffic, so a 100 mm compacted sub-base is usually enough; use 150 mm if the ground is soft or the patio will take heavy planters or features.
The MOT Type 1 Calculator gives you tonnes, bulk bags and 25 kg bags for your patio area and chosen depth.
The formula
Tonnes = Patio area (m²) × Depth (m) × 2.0 × (1 + wastage %)
Use 0.10–0.15 m depth for patios.
Worked examples
Family patio
- Patio 5 m × 4 m = 20 m².
- Compacted depth 100 mm = 0.10 m.
- Volume = 20 × 0.10 = 2.0 m³.
- Tonnes = 2.0 × 2.0 = 4.0 tonnes.
- With 10% wastage: 4.0 × 1.10 = 4.4 tonnes.
Order about 4.5 tonnes of MOT Type 1.
Patio sub-base build-up
A typical patio build-up is: compacted subsoil, 100–150 mm MOT Type 1 sub-base, a 30–50 mm sharp sand or mortar bedding layer, then the paving slabs.
Compact the Type 1 in two layers with a vibrating plate for a firm, level base. A well-prepared sub-base is the key to a patio that does not sink or move.
Frequently asked questions
All quantities on this page are estimates based on standard dimensions and densities. Real requirements vary with site conditions, material specifications and workmanship. Confirm quantities with your supplier or tradesperson before ordering. See our disclaimer for details.