Calculate how much concrete you need with this concrete calculator. Use it as a concrete slab calculator for shed bases and paths, or a concrete base calculator for footings and driveways — enter your dimensions and get the concrete volume in cubic metres, cubic feet and cubic yards, plus an approximate bag count.

Enter your pour dimensions

m
m
mm

Typical slab: 100 mm

%

Recommended: 10%

Concrete required

Volume (incl. wastage)0.79m³
Volume in cubic feet28ft³
Volume in cubic yards1.04yd³
Volume before wastage0.72m³
Approx. 25 kg bags70bags

Bag estimate assumes a 25 kg bag yields roughly 0.0114 m³ of mixed concrete. Round up when ordering.

Results are estimates only. Confirm quantities, material densities, pack sizes, product yields and specifications with your supplier or tradesperson before ordering. See our disclaimer for details.

How the calculation works

Concrete volume is simply length × width × depth. The calculator converts your depth from millimetres or inches into metres automatically, then multiplies the three dimensions to give the volume in cubic metres.

For international users, the result is also shown in cubic feet (1 m³ = 35.31 ft³) and cubic yards (1 m³ = 1.31 yd³), the units most ready-mix suppliers outside the UK quote in.

Because excavations are never perfectly level and some concrete is always lost in the mixer or pump, a wastage allowance is added. Ten per cent is standard for slabs and footings; you can adjust it to suit your pour.

Worked example

A shed base 3 m long, 2.4 m wide and 100 mm deep, with 10% wastage:

  1. Convert depth: 100 mm = 0.1 m
  2. Volume = 3 m × 2.4 m × 0.1 m = 0.72 m³
  3. Add 10% wastage: 0.72 × 1.10 = 0.79 m³
  4. In imperial: 0.79 m³ × 35.31 ≈ 27.9 ft³ (about 1.04 yd³)

You would order roughly 0.8 m³ of concrete — round up to 1 m³ for ready-mix, or about 70 × 25 kg bags.

Practical guidance on wastage

Ten per cent is the standard wastage allowance for slabs and footings, covering uneven excavation, spillage and over-pour. Running short mid-pour creates a weak cold joint between batches, so it pays to order slightly too much. For ready-mix, round up to the nearest quarter or half cubic metre; for bagged mix, round up to the next whole bag.

Common unit conversions

  • 1 m² of slab at 100 mm thick0.1 m³ of concrete
  • 1 m² of slab at 150 mm thick0.15 m³ of concrete
  • 1 cubic metre of concrete35.31 ft³ / 1.31 yd³
  • 1 cubic metre≈ 90 × 25 kg bags of dry mix
  • 1 × 25 kg bag of dry mix≈ 0.0114 m³ of mixed concrete