Mortar is a mix of sand, cement and water that binds bricks and blocks together. The mix ratio sets the strength and workability: a 1:3 or 1:4 cement-to-sand mix is common for brickwork, with 1:5 or 1:6 used for general blockwork where a weaker, more flexible mortar is acceptable.

To estimate materials, work out the finished mortar volume you need, then apply a 1.33 dry-volume factor (because the dry ingredients bulk up once mixed with water) and split the result by your mix ratio to find the cement and sand.

The Mortar Calculator and Sand & Cement Calculator below turn wall dimensions or a finished mix volume into litres, cement bags and sand tonnes in one step.

The formula

Dry volume = Finished mortar volume × 1.33

Then split the dry volume by the mix ratio to find cement and sand.

Worked examples

Mortar for a brick wall

  1. Wall 10 m², single-skin brickwork ≈ 0.026 m³ mortar per m².
  2. Finished mortar = 10 × 0.026 = 0.26 m³.
  3. Add 10% wastage: 0.26 × 1.10 = 0.286 m³.
  4. Dry volume = 0.286 × 1.33 = 0.380 m³.
  5. At 1:4, cement = 0.380 ÷ 5 = 0.076 m³, sand = 0.304 m³.
  6. Cement = 0.076 × 1,440 ≈ 110 kg (about 5 × 25 kg bags); sand = 0.304 × 1,600 ≈ 486 kg ≈ 0.49 t.

Roughly 5 bags of cement (25 kg) and 0.49 t of sand.

Step-by-step method

1. Work out the finished mortar volume you need — either from the wall area × mortar per m² (about 0.026 m³ for brickwork, 0.012 m³ for 100 mm blockwork) or as a stated mix volume.

2. Multiply by 1.33 to get the dry volume of sand and cement combined. This factor accounts for the voids that fill with water and the bulking of the dry materials.

3. Split the dry volume by your mix ratio. For a 1:4 mix, cement is one part in five and sand is four parts in five.

4. Convert the cement volume to kg using a density of about 1,440 kg/m³, then to 25 kg bags (round up). Convert the sand volume to tonnes using about 1,600 kg/m³.

5. Add 10% wastage for spillage, mixing losses and mortar left in the mixer.

Common mix ratios and their uses

1:3 (cement:sand) — a strong mix for engineering bricks and dense blockwork where high strength is needed.

1:4 — the general-purpose bricklaying mortar, strong enough for most facing brickwork and easy to work.

1:5 — a common blockwork mortar, slightly weaker and more flexible to suit the larger units.

1:6 — a weaker general-purpose mortar for internal blockwork and non-load-bearing walls. Weaker mortars are more flexible and less likely to crack as the building moves.

Measurement and unit conversion

Work in cubic metres for the finished mortar volume. A litre is 0.001 m³, so 260 litres = 0.26 m³. The dry-volume factor (1.33) and the densities (cement 1,440 kg/m³, sand 1,600 kg/m³) then convert to weights you can order.

A 25 kg bag of cement is roughly 0.017 m³ by volume, so dividing the cement volume in m³ by 0.017 gives an approximate bag count — round up to the nearest whole bag.

Sand is sold by the tonne or by the bulk bag (roughly 0.5–0.8 m³). Confirm the actual bulk-bag volume with your supplier, as it varies with the sand type.

Recommended wastage considerations

Allow 10% wastage for hand-mixing and laying, which covers spillage, mortar left in the mixer and over-mixing. For larger jobs with a consistent mixer setup, 5% may be enough.

Frogged bricks and absorbent clay bricks use more mortar because the frog fills and the brick draws water, so lean towards the higher allowance if you are using either.

Common mistakes to avoid

Using too strong a mix (for example 1:3) for soft or reclaimed bricks — a strong mortar can crack the bricks as the building moves. Match the mortar strength to the brick.

Forgetting the 1.33 dry-volume factor, which leaves you short of both cement and sand.

Measuring sand by the shovelful without a consistent gauge, so the ratio drifts across the mix. Use a consistent bucket or gauge box for each batch.

Adding too much water, which weakens the mortar and makes the joints slump.

Ordering and supplier guidance

Cement is sold in 25 kg bags, often by the pallet. Store bags dry and off the ground — cement that has absorbed moisture sets hard in the bag and is wasted.

Sharp sand (also called builder’s or grit sand) is the standard sand for mortar. Confirm the type and grading with your supplier, and order enough for the whole job in one delivery to keep the colour consistent.

For larger jobs, ready-mixed or silo mortar can be more consistent than site mixing, but it suits continuous laying rather than small repairs.

Safety and estimates

All quantities here are estimates based on standard mix ratios, a 1.33 dry-volume factor and typical densities. Real requirements vary with joint thickness, brick type, frog fill and workmanship, so confirm the final quantities with your supplier before ordering.

Cement is caustic — wear gloves, eye protection and a dust mask when mixing dry cement, and wash any skin contact immediately. Avoid inhaling the dust, particularly in enclosed spaces.

Frequently asked questions

All quantities on this page are estimates based on standard dimensions and densities. Real requirements vary with site conditions, material specifications and workmanship. Confirm quantities with your supplier or tradesperson before ordering. See our disclaimer for details.

Use the Mortar Calculator

Skip the manual maths — enter your dimensions into the Mortar Calculator and get an instant estimate with a wastage allowance built in.

Open the Mortar Calculator

Related calculators

Related guides